Gallery

Seventh Floor

Columns Work Completed and Bottom work started for Floor Slab.

Sixth Floor

Floor Slab Completed

Fifth Floor

Slab work completed and Started Brick Work From in First Floor

Fourth Floor

Columns Work Progressing

Third Floor

Columns Work Completed

Second Floor

Second Floor Completed

First Floor

First Floor Work Progressing

Inside Progress

Ground Floor Inside Progressing & First Floor Slab Work 50% Completed

First Floor

First Floor Slab Work Progressing

Column Work

Basement Roof Slab Work Completed and Ground Floor Column Work Progressing

Basement & Ground Floor Work

Basement Work Completed and Ground Floor Work Progressing

Basement Slab Work

Basement Roof Slab Work Progressing

Shuttering Work

Ready for Shuttering Work